The Clean Energy Regulator's REC Registry is now accepting STC applications for mid-scale solar: systems between 100 kW and 1 MW installed from 1 October 2026.
For up-to-date official information about Mid-Scale Solar, please visit: cer.gov.au
Eligibility requirements for new systems
To be eligible for STCs, a newly installed system must meet the CER's requirements. Mid-scale systems carry extra documentation on top of the standard list.
In addition to standard PV STC requirements, a mid-scale solar PV system (100 kW to 1 MW) must:
obtain:
an as-built structural engineering report
an electrical single line diagram
a connection agreement
be classified as mid-scale solar (100 kW to 1 MW)
comply with metering and system design arrangements for multiple related solar installations at a site or adjacent sites
An accredited designer is not required for a mid-scale system.
Don’t forget, the same requirements for small-scale PV systems still apply to your mid-scale solar projects
have STCs created within 12 months of installation
use panels and inverters on the Clean Energy Council (CEC) list of approved components
meet Australian and New Zealand standards
be installed by a Solar Accreditation Australia (SAA) accredited installer accredited for the installation type
use new components that haven't been installed before or used in another STC or LGC claim
comply with all local, state, territory and federal requirements, including electrical safety
What the SRES expansion changes
Under the SRES expansion, C&I solar systems up to 1MW can now earn STC incentives. The rules that matter most, from the CER's eligibility guidance:
Capacity is measured across related systems. A mid-scale system has a total capacity over 100 kW and up to 1 MW, counting related solar PV systems and related power stations. Whether systems are related depends on location, ownership, electrical configuration, metering and network connections. Separate meters or installation dates don't automatically make systems separate.
Over 1 MW is out. If total related capacity exceeds 1 MW, the installation can't create STCs, and a larger project can't be installed or claimed in stages to get STCs on the first 1 MW. It may be eligible for LGCs under the large-scale scheme instead.
Additions can qualify. An installation under 100 kW can be mid-scale if the total related capacity exceeds 100 kW. When an existing system is extended, STCs apply only to the capacity added from 1 October 2026, not the original system.
Deeming is fixed at five years. Small-scale systems are deemed for the remaining years to 2030. Eligible mid-scale systems get a fixed five-year deeming period through to 2030.
Planning and approval evidence comes first. Applicants must show that applicable planning and approval requirements have been met before STCs can be created.
STCs may affect other certificates. If you apply for STCs for a mid-scale system, you may not be able to create LGCs or REGO certificates for the deeming period. Raise this with your client before you lodge.
Talk to Us about Mid Scale Solar STCs
We've helped accredit more than 550 power stations, more than any other provider in Australia. Through that experience, we've developed a deep understanding of what the regulator requires for systems of this size, and we bring that knowledge directly to mid-scale STC claims.
Get it right the first time: our Geo/Onsite platform takes your team through every job with a checklist for each stage, and our team cross-checks the paperwork.
Payment on your terms. Take cash fast when you need it, or a higher return when you can wait.
If you have mid-scale systems installed since 1 October or planned on your pipeline, now is the time to claim them. See how mid-scale claims work with GET on our Mid-Scale Solar STCs page, or talk to our commercial team about your first submission.